TL;DR
TL;DR: Add an existing-conditions clause to your BIM execution plan that fixes capture method, measured and represented LOA with a confidence level, LOD per discipline, coordinate system and survey control, formats, deliverable dates, acceptance testing and data ownership. Under ISO 19650 it answers the level of information need, acceptance criteria and delivery dates in the EIR. Our published figures (±5mm registered accuracy, ±10mm at LOD 300, ±6mm at LOD 400) show the level of detail to ask any provider for.
The clause most BIM execution plans are missing is one that governs the existing building itself: how it will be captured, how accurate the point cloud and the model must be, what gets modeled for each discipline, which coordinate system and control it ties to, what formats arrive and when, how the data is tested before anyone accepts it, and who owns it afterward. Many plans spend pages on authoring software and naming conventions, then reduce existing conditions to "survey by others." Every renovation model is drawn on top of that background, so leaving it unspecified leaves the project's foundation unspecified. Below is why the gap exists, where the clause fits in the ISO 19650 framework, and a fill-in template you can paste into your BEP.
Why do BIM execution plans skip existing conditions?
Because each standard the plan relies on points back at the plan. The BIMForum LOD Specification says it "does not replace a project BIM Execution Plan (BIMXP), but rather is intended to be used in conjunction with such a plan," and it defines what is modeled, not how closely it matches the building. The USIBD C120 Level of Accuracy guide defines accuracy but deliberately does not prescribe methods, and states that "a well-defined execution plan is key to obtaining the required LOA."
So LOD defers to the plan, LOA defers to the plan, and the plan often defers to whoever shows up with a scanner. The result is a design team modeling against a point cloud nobody specified, with no agreed test for whether it is good enough.
Where does the clause fit under ISO 19650?
ISO 19650 works with a set of information requirements: organizational, asset and project information requirements (OIR, AIR, PIR), and exchange information requirements (EIR) set for each appointment. Part 2 introduces the BIM execution plan, the master information delivery plan and task information delivery plans.
The UK BIM Framework's Guidance Part 2 describes the sequence. The appointing party develops appointment-specific EIR and issues them with the tender; the prospective lead appointed party returns a pre-appointment BEP that works through each requirement and responds "to the level of information need, acceptance criteria and delivery dates set by the appointing party." The guidance defines the level of information need as a framework for "the quality, quantity and granularity of information," and says an information exchange "is completed when the information receiver accepts the information."
That gives the existing-conditions clause a clear home:
| Clause item | ISO 19650 concept it answers | Reference to cite |
|---|---|---|
| Capture method and coverage | Information production methods and procedures | Provider's method statement |
| Registered accuracy and LOA | Level of information need (quality) | USIBD LOA |
| LOD per discipline | Level of information need (granularity) | BIMForum LOD Specification |
| Coordinate system and survey control | Project information standard | Survey control report |
| Formats | Project information standard | Named file formats and versions |
| Deliverable schedule | Delivery dates and information delivery milestones | MIDP / TIDP |
| Acceptance testing | Acceptance criteria | USIBD LOA validation methods |
| Data ownership | Appointment terms | Contract and project information protocol |
If the owner issues no EIR, the guidance advises the prospective lead appointed party to consider developing a BEP "which anticipates the EIR." The same logic applies when the EIR is silent on existing conditions: the design team writes the clause itself rather than waiting for one.
What should each part of the clause say?
Capture method. Name the method, the areas in and out of scope, and how inaccessible areas are handled. Leave the equipment to the provider; the LOA guide says "the decision of which means and methods shall be used to achieve a specified LOA should remain with the building documentation professional." You control the result.
Registered accuracy and LOA. The USIBD LOA framework splits accuracy into measured accuracy (the point cloud) and represented accuracy (the model), and the C120 guide says both should be specified when measurements are processed into a deliverable. State each level, whether it is absolute or relative, and the confidence level; the guide uses 95 percent, which it ties to 2 sigma. USIBD has since released a newer LOA specification than the C120 guide quoted here, so name the version in the clause. Our ±5mm accuracy guide explains what an accuracy figure does and does not cover.
LOD per discipline. Set LOD by element group, not for the whole model. Our LOD 200 vs 300 vs 400 comparison shows how to split levels by area.
Coordinate system and survey control. Say who establishes control, which datums or project grid apply, and whether the model origin must match the survey. A cloud registered to an arbitrary origin is internally consistent and useless for tying new work to site.
Formats and schedule. Name the point cloud formats (our file formats guide compares E57, RCP, LAS and PTS), the modeling platform and version, and tie each deliverable to a date or MIDP milestone so the background arrives before design needs it.
Acceptance and ownership. Choose the validation method and pass condition before capture starts, and decide who owns and may use each part of the data. Both are covered below.
What does the clause look like as a template?
Paste this into the existing-conditions section of the BEP, or into the EIR if you are the owner. Brackets are blanks to fill; nothing in it is a recommended value for your building.
EXISTING CONDITIONS INFORMATION
1. CAPTURE METHOD AND COVERAGE
Capture method: [ ] Mobile [ ] Terrestrial (tripod) [ ] Both
Areas in scope: ______________________
Areas excluded: ______________________
Inaccessible areas: documented with photos and listed in the
registration report; not modeled unless listed in Table EC-1.
2. ACCURACY (USIBD LOA, version: ______)
Measured accuracy (registered point cloud): LOA____
Represented accuracy (model): per Table EC-1
[ ] Absolute [ ] Relative, relative to: ______________________
Confidence level: stated at 95 percent (2 sigma) unless noted
Provider's stated registered accuracy: ______ at ______ sigma
3. LEVEL OF DEVELOPMENT (BIMForum LOD Specification, edition: ______)
Table EC-1: element group | LOD | measured LOA | represented LOA
Elements not listed in Table EC-1 shall not be modeled.
Concealed elements, where modeled, shall be flagged as not
field-verified.
4. COORDINATE SYSTEM AND SURVEY CONTROL
Control established by: [ ] Owner's surveyor [ ] Provider
Horizontal datum / projection: ______________________
Vertical datum: ______________________
Project base point and survey point: ______________________
Control report delivered with: control point list, residuals,
photos of control points.
5. FORMATS
Point cloud: [ ] E57 [ ] RCP [ ] LAS [ ] PTS
Model: ______________ (platform), version ______
2D: [ ] DWG [ ] PDF
Registration and QC report: [ ] PDF
6. DELIVERABLE SCHEDULE
Capture window: ______________________
Registered point cloud due: ______ after capture
Model due: ______ after capture, or by MIDP milestone ______
7. ACCEPTANCE TESTING
Measured validation: [ ] A no data check [ ] B overlapping data
sets [ ] C independent measurements or methods
Represented validation: [ ] A no check [ ] B double check
[ ] C triple check
Check locations and number: ______________________
Pass condition: ______________________
Review period: ______ after delivery
Failure: provider corrects at ______ cost within ______
8. DATA OWNERSHIP AND USE
Owner of raw scan data: ______________________
Owner of registered point cloud and model: ______________________
Licence to design team and contractors: ______________________
Provider retention period: ______________________
Hosting and access after close-out: ______________________For a fuller scope around this clause, see our scope of work template for scan to BIM, the complete guide to a 3D laser scanning scope of work and how to write a 3D scan deliverable spec.
How would ZEALOT's published figures fill the blanks?
Here is how our published numbers land in the template, as an example of the detail to ask any provider for:
| Template line | What we state |
|---|---|
| Provider's stated registered accuracy | ±5mm registered accuracy; the manufacturer states 5 mm at 1 sigma (NavVis VLX3) |
| Represented accuracy | Model faces within ±10mm of the registered cloud at LOD 300, ±6mm at LOD 400 |
| Point cloud formats | E57, RCP, LAS or PTS |
| Registered point cloud due | 3 to 5 business days after capture for a typical single building |
| Model due | LOD 200 in 10 to 15 business days for ~100,000 sq ft; LOD 300 in 3 to 5 weeks |
Note the confidence levels. The manufacturer statement behind our scanner is given at 1 sigma, while LOA ranges are specified at 2 sigma. Line 2 of the template asks for the sigma so nobody reads a 1-sigma number straight into a 2-sigma table, ours included.
How should acceptance testing work?
The LOA framework gives three choices for validating measured accuracy: no data check, check by overlapping data sets, or check by independent measurements or methods. Represented accuracy has its own three: no check, double check, or triple check. If the clause does not choose, "no check" is a legitimate reading.
Two further points from the UK BIM Framework guidance are worth writing in. Acceptance criteria should be checkable, including that "any definition for a value, either precisely or by a range, is satisfied." And the exchange is not complete until the receiver accepts the information, so name who reviews the delivery, how long they have, and what happens on a failure. Our point cloud QA guide lists the checks worth running on the cloud before modeling starts.
Who should own the existing-conditions data?
Whoever the contract says, which is why the contract has to say it. Separate ownership from licence: an owner may own the registered cloud and model while the design team and trade contractors hold a licence to use them for this project. Treat the raw scans, the registered cloud, the model and the control data as four separate items, because they are often held by different parties and needed at different times. Keep the registered cloud and control report with the project's shared information, so the next renovation starts from them. If the data needs to stay accessible after close-out, name the hosting arrangement; see our point cloud hosting service for one option.
What should you do before the next BEP goes out?
Fill in the template with your engineers, attach Table EC-1, and send it with the tender so every provider prices the same thing. If you want a second read, send us the scope. We return scan-to-BIM quotes within one business day, and if you are unsure where LOD should change across the building, we will mark up a floor plan with recommended LOD zones. Contact us to start.
Sources
- Wikipedia, ISO 19650: parts of the series, OIR, AIR, PIR and EIR, BIM execution plan and delivery plans in Part 2.
- UK BIM Framework, Information management according to BS EN ISO 19650, Guidance Part 2: Processes for Project Delivery, Edition 4: EIR and pre-appointment BEP sequence, level of information need, acceptance criteria, completion of information exchange.
- U.S. Institute of Building Documentation, Level of Accuracy (LOA): announcement of the current LOA specification release.
- U.S. Institute of Building Documentation, Document C120, Level of Accuracy (LOA) Specification Guide, Version 2.0: measured and represented accuracy, confidence level, validation methods, role of the execution plan.
- BIMForum, Level of Development (LOD) Specification: relationship to the BIM execution plan.